If the path A-B-E-F-G has a total duration of 17 days, what is the value of E?

Enhance your quantitative skills with the PHFO Quantitative Analysis for Business Exam. Prepare with multiple choice questions, accurate hints, and detailed explanations. Success is one step away!

Multiple Choice

If the path A-B-E-F-G has a total duration of 17 days, what is the value of E?

Explanation:
The total duration along a path is the sum of all activities on that path. For the path A-B-E-F-G, the total is A + B + E + F + G, which is given as 17 days. The durations of the other activities on this path—A, B, F, and G—add up to 14 days. To reach the total of 17 days, E must be 17 − 14 = 3 days. So the value of E is 3 days. If E were any other value, the path total would differ from 17 days.

The total duration along a path is the sum of all activities on that path. For the path A-B-E-F-G, the total is A + B + E + F + G, which is given as 17 days. The durations of the other activities on this path—A, B, F, and G—add up to 14 days. To reach the total of 17 days, E must be 17 − 14 = 3 days. So the value of E is 3 days. If E were any other value, the path total would differ from 17 days.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy